Client: U.S. General Services Administration
Contract: Arraj Courthouse 1st Floor Door Installation Project
Contract Period: March 2018 – May 2018
Contract Amount: $11,651
Description of Work: Procured and installed a new door frame for the judge’s office. The new door frame was procured to match existing facility finishes. Installed GSA provided door and new lockset. The new door frame was moved to a new location, requiring repair of drywall in new and old door locations. The judge’s office area was painted.