Client: U.S. Army Corps of Engineers
Contract: Schriever Air Force Base Chiller Plant Optimization
Contract Period: September 2019 – 2021
Contract Amount: $2,984,692
Description of work: This project consists of modifications to the existing Central Chiller Plant located in Building 600 at Schriever Air Force Base near Colorado Springs, Colorado. The modifications of Building 600 will include automating the chiller plant, adding optimization controls, and revising the cooling tower sump fill controls. The existing Chiller Plant is comprised of varying capacities and efficiencies, aged cooling towers, and manual controls via plant operators, of the entire chilled water system. The system is critical to Base operations and currently provides 42 F chilled water with a minimum of two chillers and associated pumps, CSOC and JNTF secondary pumps, and towers and associated pumps operating at all times to provide a N+1 redundant system operating 24/7 to serve the base, requiring 99.9% uptime.
GSA Custom House Courtroom Ceiling Project
Client: U.S. General Services Administration
Contract: GSA Custom House Courtroom Ceiling Project
Contract Period: August 2019 – December 2019
Contract Amount: $89,179.35
Description of work: Replace the acoustic ceilings in courtrooms A, B, C, D, E, & F in the U.S. Custom House Courtroom in Denver, Colorado
Heat Plant Project for Air Force Academy
Client: United States Air Force Academy
Contract: Heat Plant Project
Contract Period: September 2018 – October 2019
Contract Value: $4,286,346
Description of Work: Improve the reliability, safety and efficiency of the Academy heat plant. The high temperature hot water (HTHW) pumps are approximately 30 years old and repair parts are no longer available. Several of the valves are in poor condition and do not close off when necessary to repair equipment. This project includes replacing 11 HTHW pumps, piping, electrical gear to support the new pumps, VFD’s, temporary boilers and fuel for the temporary boilers during the shutdown, new equipment pads and abatement of asbestos insulation.
NIST Roofing Project
Client: National Institute of Standards and Technology
Contract: NIST Roof
Contract Period: September 2018 – September 2019
Contract Value: $2,248,554
Description of Work: Fully replace the roofs on Building 4, Building 5, Building 21, Building 25, and Building 24 at NIST. Partially replace the roof at the Building 1 library, and Building 2. Replace skylights on Building 2 and Building 25. Remove abandoned equipment, replacement of one roof top unit, relocation of misc. exhaust fans. Procure and install two new exhaust fans. Replace, install and certify lightning protection. Install new primary and secondary roof drains, gutters and down spouts along with snow stops. This work will include TPO roofing, spray foam roofing, lightning protection, electrical, mechanical and controls.
Construction Services for Aerospace Corporation
Client: The Aerospace Corporation
Contract: Construction Services
Contract Period: September 2018 – September 2019
Contract Value: $250,000
Description of Work: Provide pre-construction, construction administration and general contracting services on various types of construction projects on an as-needed and emergency basis for the Colorado Springs facility. The Colorado Springs facility is a two-story 78,000 sq. ft. office building with 388 on-grade parking spaces. Typical types of projects include interior tenant improvements, modular furniture installations / audio visual upgrades, electronics / computer lab modifications, conference rooms / seminar rooms / classrooms , secure office bays & rooms , site improvements / infrastructure upgrades, building exterior repairs, data / network upgrades & installations, building equipment replacements / building system upgrades and modifications.