Client: Pueblo Chemical Depot
Contract: Warehouse Asbestos Mitigation Project
Contract Period: September 2018 – February 2019
Contract Value: $1,394,951
Description of Work: On March 24, 2018 one structure in the warehouse area of PCD (Building 576 – 92,000 sf) was completely consumed by fire. A second structure (Building 581) was partially consumed by fire. The western half of Building 581, consisting of approximately 41,000 square feet was destroyed. The scope of this project is to safely remove all debris in the regulated work areas associated with Building 576 and Building 581. The eastern half of building 581, including the firewall will also safely be demolished. The foundations will remain in place. All materials will be characterized, properly packaged and transported to an acceptable disposal site. All work will be completed in accordance with applicable regulations and coordination.